Data center electricity use could double by 2030, IEA says
The IEA cites large data center project pipelines in Texas, Virginia, Finland and the U.K. In several regions, the combined capacity of data centers waiting to connect exceeds current peak demand.
Full article
Without grid upgrades, power networks could become more congested and less reliable, the IEA said.
New projects could face longer waits to connect, while generators could be forced to cut output when the grid cannot meet demand.
Peak electricity demand is projected to rise 40% to 50% by 2035, according to the IEA. Under the Stated Policies Scenario, grids should be expanded by 26 million kilometers of new lines by 2035, while about 16 million kilometers of existing lines need to be replaced or refurbished. Supplies of copper, cables and transformers are already tight, the IEA said.